Case Study — HPC / AI Infra

SaveMe! AI ServerInfrastructure

Sizing, designing and procuring a four-server on-premise stack, including an NVIDIA H200 NVL AI node, for a platform launching at 100,000–150,000 active users.

Role
IoT Engineer & Server Manager
Company
Mitra Teknologi Gemilang
Year
2026
Status
Vendor RFQ
Network topology diagram — coming soon
Fig. 1 — Rack, network and power topology
4
Dedicated servers
100K–150K
Active users, initial tier
~25%
Lower est. AI node cost
1.76×
GPU memory per node

01

The Challenge

  • SaveMe! needed its own on-premise infrastructure: an application backend, AI inference on GPU, realtime connections, and a database with file storage.
  • It had to launch for 100,000–150,000 active users, grow toward 1M without a redesign, and go through a vendor-neutral procurement with competing quotes.

02

Approach

  • Sized every service from per-tier resource estimates (CPU, RAM, GPU memory, disk) and interpolated them to the target tier.
  • Checked each server against those needs using usable capacity after RAID, and noted which resource runs out first.
  • Planned capacity tiers from 50K up to 1M active users and verified each node's upgrade path: RAM slots, GPU slots, drive bays and CPU generation.
  • Validated parts against the chassis platform, such as CPU socket generation and GPU power per slot, before the RFQ went out.

03

Four Servers, One Job Each

General

Application & API backend

2× 32-core Xeon · 128 GB DDR5 ECC · 2× 1.92 TB SSD (RAID 1)

AI

GPU inference services

2× 32-core Xeon · 512 GB DDR5 ECC · 1× NVIDIA H200 NVL 141 GB · 2× 1.92 TB NVMe (RAID 1)

Realtime

Live connections & events

1× 32-core Xeon · 64 GB DDR5 ECC · 2× 960 GB SSD (RAID 1)

Storage

Database & file storage

2× 32-core Xeon · 128 GB DDR5 ECC · 4× 3.84 TB NVMe (RAID 10)

Every node: 2× 600 GB SSD for the OS (RAID 1), 2× SFP+/SFP28 uplinks bonded with LACP, and redundant PSUs split across PDU A and B.

04

Key Decision: Storage Out, Compute In

AI nodeInitial specFinal spec
GPU1× 80 GB (H100 PCIe class)1× NVIDIA H200 NVL, 141 GB HBM3e
System RAM256 GB DDR5 ECC512 GB DDR5 ECC
Data storage4× 3.84 TB NVMe, RAID 10 (~7.7 TB usable)2× 1.92 TB NVMe, RAID 1 (1.92 TB usable)
Estimated node costBaseline~25% lower
  • The AI services run stateless inference with no database. Estimated disk need at the target tier was under 1 TB, so 7.7 TB of RAID 10 NVMe was idle capital.
  • GPU memory was the first resource to run out in the capacity model, so the savings went into compute: a 141 GB H200 NVL instead of an 80 GB card, and double the RAM.
  • The H200 NVL was priced close to the H100 PCIe at the time, while the H100 PCIe was being discontinued.
  • The upgrade path stays open: more GPUs and RAM can be added to the same chassis later. The CPU stays, since it only feeds the GPU.

05

Network, Rack & Power

  • Data network: a Layer 3 core switch with 24× SFP+/SFP28 ports. Each server bonds two ports with LACP, and VLANs separate service traffic.
  • Out-of-band management: a separate 1G switch for iDRAC/IPMI and PDU monitoring, so every server stays reachable even if the core switch fails.
  • Power: two monitored 3-phase PDUs (A and B), with each server's redundant PSUs split across both feeds, in a 42U rack at a Tier-3 colocation data center in Jakarta.

06

Procurement

  • Wrote a brand-neutral BOM and RFQ (spec-based, equivalent brands accepted) so several vendors can quote on the same requirements.
  • Set commercial terms up front: DDP pricing including VAT, import duty and logistics, plus a 3-year principal warranty with 24×7, 4-hour onsite support.
  • Prepared the RAB, an NDA step before full specs are shared, and a vendor comparison matrix targeting at least three quotes.

07

Trade-offs & Next Steps

  • Known risk: one server per role and a single core switch, so there is no node-level failover yet; disks and power are redundant. A spare switch and N+1 nodes are the next HA step.
  • Capacity figures are paper estimates. GPU memory math does not capture throughput, so load testing after deployment will confirm real capacity.
  • Open item: confirm H200 NVL support and power per GPU slot on the vendor's proposed chassis.

Budget figures and vendor quotes are confidential and left out of this page.

All Projects